DPW Completes Projects to Cover  Remaining Open-Air, Treated Water Reservoirs at Ashburton and Druid Lake

Green banner with DPW logo and text "Department of Public Works Press Release"

Today, Baltimore City Department of Public Works (DPW) Interim Director Richard J. Luna announced that both projects to cover the remaining open-air, treated water reservoirs at Ashburton and Druid Lake have been successfully completed and the new      tanks are in service. For DPW, this achievement marks the end of open-air reservoirs to store treated drinking water, adding another layer of protection to the region’s water supply.

Based on the successful completion of these tank projects, the Maryland Department of Health (MDH) and Maryland Department of the Environment (MDE) have lifted their standing precautionary advisory that recommended individuals with severely weakened immune systems should drink bottled, boiled, or filtered water related to a previous one-time positive test for cryptosporidium in September. All subsequent tests, taken on a weekly basis since then, have been negative.

“The Ashburton and Druid Lake reservoirs are an integral part of Baltimore’s water system,” said Interim Director Luna. “The successful completion of these underground tank projects, which have been in the works for nearly six years, adds a higher level of protection to the Baltimore region’s water supply, and this investment will help to ensure the continued delivery of high-quality water to residents and water customers for generations.”

The Ashburton tanks became operational on December 7, 2023, and the Druid Lake tank became operational on December 21, 2023. The remaining site work for both locations, including park amenities, is scheduled for completion in the summer of 2024.  

In addition, the City of Baltimore has met Safe Drinking Water Act requirements for three other previously uncovered reservoirs, Towson Reservoir, May 31, 2013; Montebello Filtration Plant II Reservoir, June 30, 2014; and Guilford Reservoir, July 1, 2019.

Given federal regulations require finished drinking water to be covered or receive additional treatment, the City of Baltimore has pursued these projects to cover the remaining reservoirs for several years. In 2017, DPW launched construction for the  Druid Lake Project, and started work on the Ashburton project in 2018.

Work on both projects was subject to unavoidable and extensive delays due to unforeseen site conditions, worker shortages, and supply chain delays caused by the COVID-19 pandemic. Since July 2023, DPW has been under a modified Administrative Order on Consent with the U.S. Environmental Protection Agency (EPA), which stipulated sampling for Cryptosporidium and Giardia at the formerly uncovered reservoirs.

On Thursday, September 28, 2023, DPW announced that during a routine test, the Druid Lake Reservoir revealed low levels of the microscopic parasite Cryptosporidium. As a result, MDH and MDE placed a precautionary advisory for the immunocompromised and individuals with severely weakened immune systems to drink bottled, boiled, or filtered water. DPW initiated weekly testing of both reservoirs--yielding no additional detections. DPW provided weekly test results for all samples. However, testing is no longer required now that both tanks are covered.

The EPA order also required the Ashburton tank to be in service by November 30, 2023, and the Druid Lake tank to be in service by December 30, 2023. Last month, the EPA granted a two-week extension for the Ashburton tank, which amended the completion date to December 15, 2023. Both projects were completed ahead of their amended schedules.

###

Related Stories

Baltimore City, County to Host Public Meetings to Brief Residents on Process to Identify and Report Water Service Line Material 

The Baltimore Service Line Partnership has announced two public meetings for Baltimore City and County residents to learn what water customers need to do to identify and report their water service line material. The Baltimore Service Line Partnership is a collaboration between the Baltimore City Department of Public Works (DPW) and the Baltimore County Department of Public Works and Transportation (DPWT) to address new federal regulations aimed at protecting communities from lead exposure in drinking water.

DPW Snow Update: Friday’s Trash, Recycling Collections Suspended Sanitation Yards, Residential Drop-off Center, Customer Service Office Closed Early

Due to today’s steadily falling snow, the Baltimore City Department of Public Works (DPW) Solid Waste crews are unable to conduct trash and recycling collections on Friday, Jan. 19. Monday, Jan. 22, is the anticipated make-up day for Friday’s trash and recycling collections.

Tomorrow, Saturday, Jan. 20, limited Solid Waste crews will be out addressing missed pickups from this week, if weather and road conditions permit. However, the ability to complete the routes will depend on whether the snow and ice have thawed enough for the alleys to be accessible.

DPW Holiday Schedule:  Offices, Sanitation Yards Closed New Year's Day, Monday, January 1 Christmas Tree Mulching Service, Collections Are Underway

In observance of New Year’s Day, Baltimore City Department of Public Works (DPW) Interim Director Richard J. Luna reminds residents that DPW offices and Sanitation Yards will be CLOSED Monday, Jan. 1, 2024. The holiday closure does NOT impact residential trash and recycling collections. Mechanical street sweeping, and scheduled Monday leaf collections WILL NOT be in effect.