Baltimore City Department of Public Works Director Rudolph S. Chow, P.E., today announced that on Tuesday, October 1, 2019, DPW contract workers will begin to restore the slope at the Druid Lake Dam. This work will involve the removal of 13 so-called “volunteer” trees - vegetation which has self-seeded on the base of the dam. This work will be complete in approximately 6 weeks.

Trees are not permitted along earthen dams as they can cause destabilization of the soil. In 2013 the City removed 450 trees from the dam, near the same area.

The Druid Lake Dam is constructed of clay and other soils. Its stability depends on the earth remaining stable. Tree roots reach well into the soil and loosen it, causing slope failure and the possibility of leakage and even dam failure. Such vegetation is not permitted under federal and state statutes.

Tree removal work will take place along the southeast section of the dam, which runs along Druid Park Lake Drive. Once the trees are removed, the contractor, Environmental Quality Resources LLC, will reinforce the soil, and restore stability to the slope. Grass will then be planted.

Traffic: Work on the Druid Lake Dam slope will be done from 9 a.m. to 3 p.m. in order to minimize disruption to rush hour traffic. Westbound traffic, emerging from the I-83 exit onto Druid Lake Drive, will be reduced to one lane at the dam.

Druid Lake dates back 150 years when the Baltimore City Council appropriated funds to build this drinking water reservoir. The lake was created by the construction of the earthen dam, 119 feet high and 750 feet long. At the time of its completion it was the largest such dam in the country. It still is a marvel of engineering as evidenced by its designation as a National Historic Civil Engineering landmark.

Related Stories

DPW is Now Accepting Public Comments on the Modified Sanitary Sewer Consent Decree Revised Emergency Response Plan 

The Baltimore City Department of Public Works (DPW)  has announced the release of its Revised Emergency Response Plan (ERP), a reference tool to be used by City personnel during a sanitary sewer overflow or reported building backup emergency. The Modified Sanitary Sewer Consent Decree (MCD) requires DPW to submit a revised Emergency Response Plan to protect the public health and welfare in the event of an unpermitted release, spill, or discharge of pollutants from the sewer collection system or in the event of a reported building backup.

Register Now for the Mayor's Fall Cleanup, October 26

Mayor Brandon M. Scott, the Baltimore City Department of Public Works (DPW), and the Mayor's Office of Community Affairs have announced the upcoming Mayor's Annual Fall Clean-up and Day of Service. Residents, volunteer groups, and community associations are encouraged to register now to participate in the city-wide effort to beautify neighborhoods. The event will run on Saturday, October 26, 2024, from 9 a.m. to 1:00 p.m.

Mattress and Box Spring Recycling Now Available at Quarantine Road Landfill Residential Drop-Off Center



Looking to get rid of an old mattress? Baltimore City residents can now drop off mattresses and box springs for recycling at the Baltimore City Department of Public Works’ (DPW) Quarantine Road Landfill Residential Drop-Off Center. In the coming months, DPW will expand this mattress recycling service to other Residential Drop-Off Centers across the city.